Cluster Boundary Checklist
This checklist expands the minimal list into concrete tasks, owners, required documents, timelines, acceptance criteria, and platform fields to populate.
A. Pre-launch (T-90 to T-7 days)
-
Obtain official taluk boundary & village list
- Owner: Master Franchisee / Legal
- Documents: Government taluk map (PDF), village list CSV, taluk code
- Timeline: T-90 days
- Acceptance: Taluk boundary file uploaded to OX Platform; village list matches government source.
-
Finalize OX Park location & land documentation
- Owner: Master Franchisee / Node Partner
- Documents: GPS coordinates, land ownership/lease agreement, site photos
- Timeline: T-60 days
- Acceptance: Land deed/lease uploaded; site passed site-readiness checklist.
-
Platform cluster record creation
- Owner: Platform Ops
- Platform fields to populate: ClusterID, TalukCode, ParkGPS, ParkLandDoc, VillageListRef, DefaultSettlementRules
- Timeline: T-45 days
- Acceptance: Cluster record exists and is accessible by Franchisor and Master roles.
-
Plan Nodes, Booking Centers & Outposts
- Owner: Master Franchisee
- Documents: Node location list + GPS, Booking Center operator details, tentative Outpost list
- Timeline: T-45 days
- Acceptance: Node and Booking Center list uploaded; distance validations (nodes within 10–15 km of Park; Booking Centers ≤5–7 km to local villages) pass.
-
Procurement & Dark Store setup plan
- Owner: Master / OX Inputs / OX Spares
- Documents: Dark store capacity plan, SKU list, replenishment schedule
- Timeline: T-30 days
- Acceptance: At least one Node or Booking Center stocked for pilot SKUs; replenishment SLA agreed.
-
Sub-franchisee pre-selection & training plan
- Owner: Master Franchisee
- Documents: Candidate list, KYC docs, proposed Sub agreements, training curriculum
- Timeline: T-30 days
- Acceptance: X pilot Subs approved by Franchisor and enrolled in training.
-
Banking & Settlement setup
- Owner: Platform Ops / Finance
- Documents: Master bank details, tax registrations, settlement account setup
- Timeline: T-21 days
- Acceptance: Settlement flows tested in sandbox; settlement schedule configured.
-
Regulatory & compliance checks
- Owner: Legal / Master
- Documents: Local licences, environmental clearances (if required), insurance proof
- Timeline: T-21 days
- Acceptance: All mandatory licences uploaded and verified.
B. Launch Week (T-7 to Launch Day)
-
Hardware & Connectivity readiness
- Owner: Platform Ops / Master
- Documents: POS device list, internet provider confirmation, power backup plan
- Timeline: T-7 days
- Acceptance: POS devices paired in platform; connectivity stress-test completed.
-
Training & SOP sign-off
- Owner: Master / Franchisor
- Documents: Training attendance sheets, SOP ack forms
- Timeline: T-5 days
- Acceptance: All pilot Subs and Node staff complete mandatory training and acknowledged SOPs.
-
Mock transactions & settlement test
- Owner: Platform Ops / Finance
- Documents: Test transaction logs, settlement reconciliation report
- Timeline: T-3 days
- Acceptance: End-to-end transaction flow (booking → payment → settlement) passes QA.
-
Pilot marketing & farmer outreach
- Owner: Master / Marketing
- Documents: Outreach plan, demo event schedule, FPO/co-op contacts
- Timeline: T-3 days
- Acceptance: At least Y farmers registered for pilot events; contact list uploaded.
C. Launch Day (T=0)
-
Go-live checklist
- Owner: Master / Platform Ops / Franchisor (observer)
- Tasks: Enable cluster on platform, activate pilot Subs, open booking channel, start dark-store replenishment
- Acceptance Criteria: Bookings visible in platform ledger; first bookings processed successfully; at least one fulfillment executed.
-
Operational monitoring (first 72 hours)
- Owner: Master / Platform Ops
- Checks: Service response time, failed bookings, payment exceptions
- Acceptance: No critical exceptions (>1% failed bookings) and SLA response times within configured thresholds.
D. Post-launch Stabilization (T+1 to T+90 days)
-
Weekly reconciliation & ops review (first 4 weeks)
- Owner: Master / Finance / Platform Ops
- Documents: Weekly settlement report, discrepancy logs
- Acceptance: Settlement mismatches <0.5% after reconciliation.
-
Inventory & dark-store tuning
- Owner: Master / OX Inputs / OX Spares
- Tasks: Adjust SKUs, reorder points, lead times based on demand
- Acceptance: Dark-store fill rate >90% for pilot SKUs.
-
Sub & farmer feedback loop
- Owner: Master / Franchisor
- Tasks: Collect NPS, fix critical SOP gaps, retrain if needed
- Acceptance: Farmer NPS ≥ target (configurable) and reduction in operational complaints month-over-month.
-
Performance review & scale decision (T+90 days)
- Owner: Franchisor / Master
- Criteria: GMV targets, SLA compliance, farmer adoption, inventory KPIs
- Decision: Green (scale), Amber (optimize + extend pilot), Red (pause & remediate)
E. Platform Fields to Populate (minimum)
- ClusterID, TalukCode, ClusterName
- ParkGPS, ParkLandDocRef, ParkCapacity
- NodeList: [Node ID, GPS, Capacity, HostName]
- BookingCenters: [CenterID, VillageName, OperatorID, GPS]
- Outposts: [OutpostID, GPS, Seasonality]
- VillageListRef (official village code list)
- SurveyNumberMapping (land -> SurveyNo -> Owner)
- MachineryInventory: [MachineID, Type, Owner, BaseNode, SerialNo]
- SubFranchiseeRoster: [SubID, ServiceType, KYCRef, ApprovedBy, ActivationDate]
- SettlementAccountRefs (Master, Subs)
- SLA Configs (response_time_minutes, max_distance_km)
F. KPIs to Monitor (first 90 days)
- Territory GMV (monthly)
- Active Subs (count) & activation rate
- On-time service fulfillment (% within SLA)
- Dark-store fill rate (% for pilot SKUs)
- Farmer NPS
- Average platform settlement accuracy (% matched transactions)
- Avg response time for machinery requests (minutes)
G. Sign-off
- Master Franchisee Representative: __________________ Date: _________
- OX Franchisor Representative: _______________________ Date: _________
- Platform Ops Representative: ________________________ Date: _________