Implementation Plan

Phase 2 financial modeling deliverables, timeline, and budget.

A. Phase 2 Activities

#ActivityDurationResourcesCost (₹)
1Financial Model Development3 weeksAnalyst + CA1,50,000
2Scenario Analysis2 weeksTeam + Expert1,00,000
3Partner Structure Design2 weeksLegal + Finance1,25,000
4Risk Assessment1 weekConsultant75,000
5Documentation & Validation1 weekTeam50,000
TOTAL9 weeks₹5,00,000

Timeline Gantt Chart

Week:        1    2    3    4    5    6    7    8    9
│ │ │ │ │ │ │ │ │
Financial ████████████████████
Model │ │ │ │ │ │ │ │ │
│ │ │ │ │ │ │ │ │
Scenario │ │ │ ████████████
Analysis │ │ │ │ │ │ │ │ │
│ │ │ │ │ │ │ │ │
Partner │ │ │ │ │ ████████████
Structure │ │ │ │ │ │ │ │ │
│ │ │ │ │ │ │ │ │
Risk │ │ │ │ │ │ │ ██████
Assessment │ │ │ │ │ │ │ │ │
│ │ │ │ │ │ │ │ │
Documentation│ │ │ │ │ │ │ │ ██████

B. Key Deliverables

#DeliverableStatus
1Complete financial projections (all scenarios)✅ Complete
2Partner investment proposals✅ Complete
3Risk mitigation strategies✅ Complete
4Board-ready investment presentation🔄 In Progress
5Loan application documentation📋 Pending

C. Resource Allocation

RoleEngagementWeekly HoursTotal Cost (₹)
Financial Analyst9 weeks402,25,000
Chartered Accountant4 weeks2080,000
Legal Counsel2 weeks1575,000
Industry Consultant1 week2050,000
Project Coordinator9 weeks2070,000
TOTAL₹5,00,000

D. Next Steps (Phase 3)

StepActionOwnerTimeline
1Board presentation and approvalCEOWeek 10
2Partner outreach initiationBD TeamWeek 11-12
3Term sheet negotiationsLegal + FinanceWeek 13-16
4Due diligence preparationFinance TeamWeek 17-20
5Loan application submissionCFOWeek 21
6Equipment procurement initiationOperationsWeek 24

E. Success Criteria

CriteriaTargetMeasurement
Financial model accuracy±10% varianceActual vs projected
Partner interest3+ term sheetsNumber of offers
Board approval100% consensusVote outcome
Timeline adherenceUnder 1 week delaySchedule variance
Budget complianceUnder 5% overrunCost variance

F. Assumptions & Dependencies

Key Assumptions

  1. Market conditions remain stable
  2. Interest rates stay within 11-14% range
  3. Equipment prices don't increase more than 5%
  4. Regulatory environment unchanged
  5. Partner pipeline remains active

Dependencies

DependencyImpactMitigation
Board approvalGate for Phase 3Early stakeholder alignment
Market data accuracyModel reliabilityMultiple data sources
Partner availabilityInvestment timelineMaintain pipeline
Legal documentationAgreement timelineParallel workstreams

G. Revision History

VersionDateChangesAuthor
1.0Initial financial modelFinance Team
1.1Updated revenue projectionsAnalyst
1.2Added partner structuresBD + Legal
2.0Comprehensive revisionProject Team